How to Create and Record a Critical Area Site Plan aka a CASP

Know what’s on your land. Document the restrictions. Understand which future options an approved plan may protect.

From Anton Stetner’s conversation with Mike Appleby · October 22, 2026
Official sources checked October 22, 2026 · Unincorporated county examples

Watch the full episode and explore its three companion resources →

The short answer

Research. Prepare. Approve. Record.

A CASP identifies critical areas and protection requirements on a property. In Snohomish County, get the required plan approved by PDS before signing or recording, then return recording proof before permit issuance. King County uses its own site-plan and notice-on-title requirements.

An approved plan can matter. Recording alone is not a blanket guarantee of future development rights. The applicable code, approval conditions and proposed activity control the answer.

  1. Confirm jurisdiction & existing records
  2. Establish critical areas & proposal
  3. Get the required county approval
  4. Execute & record the accepted document
  5. Return proof & meet permit conditions
Unincorporated Snohomish County

The CASP pathway

PDS review → approved CASP → Auditor recording → proof to PDS.

Unincorporated King County

The King County pathway

Critical-area review → site plan → required notice / tracts → recording proof.

Start with the jurisdiction, then the land

Washington requires counties and cities to protect critical areas. There is no single statewide CASP form or universal wetland buffer. Confirm whether the property is in unincorporated county jurisdiction or inside a city. An Edmonds mailing address, for example, does not establish which permitting office controls the parcel.

Critical areas include wetlands, aquifer recharge areas, fish and wildlife habitat, frequently flooded areas, and geological hazards. A wetland or stream on a neighboring parcel can still affect your land. County maps help screen for issues; a blank map is not a clean bill of health. Use the reports and determinations required for the actual site and proposal.

The property lesson from the podcast

In the October 22, 2026 conversation with Anton Stetner, Mike Appleby describes a five-acre property in the Edmonds area with a previously recorded critical-area plan. At 40:40–42:20, he recalls 25-foot wetland setbacks and a purchase around $1.6 million, compared with his estimate of roughly $400,000 without the earlier plan.

Those are Mike’s recollections and a hypothetical value comparison, not an independently verified appraisal or a current buffer standard. The episode does not identify the parcel, recording number, permitting jurisdiction, or approval conditions. The practical takeaway: retrieve the actual recorded plan before deciding what a property can support or what it is worth.

The useful question is what the approved document protects, which restrictions it creates, and whether your intended use fits its conditions. The answer differs between Snohomish County and King County.

What can an approved plan actually protect?

Snohomish County’s SCC 30.62A.160(6) allows activity consistent with a previously approved CASP to be governed by that plan’s terms, provided the required wetlands, habitat areas and buffers were identified and permanently protected. Consistency means no proposed changes to protective measures, increased impacts, or direct impacts to critical areas or buffers. That is a conditional protection worth investigating.

Recording also documents restrictions. A protected area is not spare yard space to clear later. The document does not by itself approve a house, subdivision, septic system or access route, and it does not freeze every regulation. Ask the permitting authority to confirm in writing how an existing plan applies to the specific work you propose; use a land-use attorney for a disputed vesting or title question.

King County’s Critical Areas Designation (CAD) is a different decision. Its February 2026 guidance describes a five-year determination of existence, location and classification, subject to exceptions. Typical buffer information in a CAD is preliminary. Read the actual determination and the county’s transition guidance before treating an older CAD as protecting a particular buffer width.

Assemble the evidence before drawing the final plan

Define the proposed use first: a home addition, shop, DADU, subdivision, or future sale. Then assemble one working property file. Give the same base information to the planner, biologist, surveyor and designer so the report boundaries and drawing agree.

Use a qualified wetland or habitat professional for ecological delineation and classification; use a geotechnical professional when slope or other geological hazards require it. A surveyor can resolve boundary and location questions. The permit reviewer determines which studies and plan details your application needs. A self-drawn sketch cannot substitute for required professional work.

  • Parcel number, legal description, jurisdiction and permit number, if assigned.
  • Current title report and copies of referenced CASPs, plats, easements, restrictions and amendments.
  • Available survey, prior permits, critical-area reports and written county determinations.
  • Existing lawful structures and uses, proposed work, driveway, utilities, septic and drainage constraints.
  • Field-established critical-area boundaries, applicable buffers, separate building setbacks and any approved mitigation.

Snohomish County: create, approve, then record the CASP

For unincorporated Snohomish County, start with PDS and its official CASP packet. The wetland and habitat protection requirements are in SCC 30.62A.160; geological hazards and aquifer recharge areas have separate code provisions. Ask PDS which documents apply to your project, especially if more than one critical-area type is present.

1. Search the Auditor’s records for an existing CASP or plat restrictions. Review every page and referenced amendment. The county’s NGPA / CAPA guidance explains how to search by parcel number or plat name. No recorded CASP does not prove there are no critical areas.

2. Have the required reports and drawing prepared. Complete the legal description, owner information, parcel and project identifiers, related recording references and plan. Show existing and proposed development, critical areas, buffer widths, setbacks and recognizable reference points. Label the wetland / habitat protection areas and their buffers as CAPA.

3. Submit the draft through the PDS Permit Portal for reviewer approval. Resolve corrections before signing or recording. Ask the reviewer whether your project needs this separate form or records protection through a plat or another approved plan.

4. After PDS accepts the plan, complete the required owner execution and approval fields as directed. Submit the approved document to the Auditor using the current recording instructions and fee quote. Return proof of recording to PDS before permit issuance.

5. Retain the recorded copy and approval conditions. Confirm required field marking, fencing, signs, inspections and ongoing protection. Recording is one milestone in the permit process.

Snohomish CASP drawing details that prevent rework

Use the county’s actual form. These are selected requirements from its packet; follow the full instructions and your reviewer’s corrections.

Official CASP packet: selected formatting requirements
ItemRequirement
Paper and marginsMaximum 8½ × 14 inches. First-page top margin: 3 inches; sides and bottom: 1 inch. Additional pages: 1-inch margins.
Parcel scopeOne tax parcel per CASP; the packet calls for a separate CASP for each legal lot when a project covers multiple legal lots.
DrawingStandard engineering scale, scale bar, north arrow, dimensioned boundaries and a legend.
LegibilityAt least 8-point text and ¼-inch spacing for hatching / symbols after reduction.
AppearanceNo color coding, shading, graph paper or contour lines on this recording form.

Illustrative walkthrough

Worked example: a shop on a Snohomish County parcel

Illustrative scenario, not a recorded approval: an owner proposes a 30 × 40-foot shop on one legal lot in unincorporated Snohomish County. A wetland lies along the east side. The shop footprint is 1,200 square feet; that number says nothing by itself about the allowed building area.

The biologist identifies and rates the wetland. The project team plots the accepted wetland edge, the applicable buffer, any separate setback, the shop, driveway and utility work. Existing lawful uses inside the protected area are identified. If the driveway crosses the buffer, moving the shop alone does not resolve the impact; redesign or a specifically authorized alteration may be needed.

The owner submits the CASP to PDS, resolves comments, executes the approved version, records it and supplies the recording proof. The finished file should contain the approved report, approved CASP, Auditor recording number and remaining permit conditions. Do not borrow the podcast’s 25-foot dimension for this new project.

King County: site plan, notice on title and sometimes a tract

For unincorporated King County, use the county’s process rather than submitting Snohomish’s CASP form. A CAD can establish critical-area information before a development application; it is not a construction permit. KCC 21A.24.180 requires applicable critical areas, buffers and setbacks to be delineated on development site plans.

1. Review existing recorded restrictions and permit records. If you have a CAD, give the reviewer the full letter and date. The new CAO generally took effect February 18, 2026, with a separate shoreline transition. Ask which rules govern your application; do not infer vesting from ownership date.

2. Prepare the required critical-area reports and development site plan. Resolve ecological or geological review and any mitigation requirements with Permitting. Under KCC 21A.24.180, subdivisions, short subdivisions and binding site plans can also require separate critical-area tracts, with ownership and management provisions.

3. When required by KCC 21A.24.170, obtain the department-approved notice-on-title form and instructions. It records the presence of critical areas, buffers or mitigation and applicable limitations, including approved buffer or riparian averaging / reductions. The section has exceptions, including certain sites containing only an aquifer recharge area or erosion hazard area; let the reviewer determine applicability.

4. Complete and record the required notice with the King County Recorder’s Office. Submit proof before the department approves the development proposal, or before recording a subdivision, short subdivision or binding site plan, as the code specifies. The notice runs with the land. Keep it with the approved site plan and reports.

Illustrative walkthrough

Worked example: a King County addition beside a stream

Illustrative scenario, not a recorded approval: an owner outside city limits proposes a 20 × 24-foot addition and has a CAD letter dated October 2024. The proposed addition is 480 square feet. A stream runs beside the property.

Being within five years of the CAD is not the whole test. The reviewer checks whether it remains effective and how the current rules apply. King County’s transition guidance says CAD letters after August 2023 establish on-site existence, location and classification, while buffer regulations for applications submitted on or after February 18, 2026 must meet the new CAO. Ask the reviewer to resolve any shoreline-specific timing.

Have the plan show the addition, stream, applicable riparian area, other buffers and building setbacks. If the footprint conflicts, evaluate a revised layout or the applicable exception process before assuming the addition is allowed. Record the required county-approved notice and provide proof at the required approval stage. A recorded notice does not approve an encroachment.

Budget for the work, not just the recording stamp

As checked October 22, 2026, both counties list a standard / general document recording fee of $303.50 plus $1 for each additional page. A qualifying two-page, single-title document would therefore be $304.50. This is recording-fee arithmetic, not a CASP project quote. Confirm document classification, page count, additional titles and any extra fees with the recording office before payment.

Reports, fieldwork, survey, drafting, permit review, revisions, mitigation, legal review and installation work are separate costs. Obtain written scopes and quotes. The episode’s condominium mapping estimates are for a different process and should not be used as a CASP budget. There is no universal approval timeline: missing information, field access and review corrections can change the schedule.

Finish with a property file someone else can use

Save the recorded instrument, recording number and date, approved drawings, technical reports, written approval and conditions, amendments, and evidence of required installations. Confirm the recorded image is legible and matches the approved version. Give a buyer or future project team the actual documents.

Before a later project, compare its footprint and impacts with the approved plan. Before a sale, describe the documented approval and its conditions accurately. A recorded restriction can clarify the property’s options, but a broker’s marketing summary cannot establish development rights.

Take the next step

Bring a better property file.

A three-page PDF with printable checkboxes, space for property notes, separate county steps and clickable official sources. Bring it to your planner, consultant or county reviewer.

Download the CASP checklist (PDF) ↓

Free download · 3 pages · No signup required. A planning checklist, not a recordable instrument.

Common questions

Can I record a CASP before I have a building project?

Ask the permitting jurisdiction which application or review path is available for your objective. Snohomish’s cited recording requirement is tied to permit activity; the form alone does not establish a standalone approval path. King County offers a CAD for early critical-area information, but that is different from approval of a development project.

Does a CASP guarantee that future buffers cannot change?

No blanket guarantee applies. Snohomish County’s existing-plan protection has identification, permanent-protection and consistency conditions. King County has different CAD and vesting rules. Obtain a written property-specific determination before relying on an older plan.

Is an online map enough to prepare the plan?

Maps are a starting point. Where required, a qualified professional must establish site-specific conditions and the jurisdiction must review them. Off-site critical areas can also affect the property.

Can AskAnton approve or record my plan?

AskAnton can help you organize the property questions and next steps. Qualified professionals prepare the required technical work, the permitting authority approves it, and the county recording office records the accepted instrument.

Sources, scope and next steps

Prepared by AskAnton from the October 22 episode and the official materials linked beside each section. The Snohomish online code reviewed reports legislation through August 19, 2026; King County’s code page is updated September 9, 2026. Check later amendments, appeals, shoreline rules and the requirements that govern your application with the permitting office.

These examples cover unincorporated county processes. Cities may have different forms and approval paths. This guide provides general education, not a survey, delineation, legal opinion, county approval or guarantee of property value.

Make it specific to you

Where do you
want to go next?

Bring your question, your timing, or the details this guide did not cover. Start wherever you are.

This prepares an editable question. Send it in chat when you are ready.

Contact options →
Your conversation

Ask in your own words.

Chat uses Functional cookies. Review to enable them.

If chat still does not appear, email the team. Nothing has been sent from this page.

You’re chatting with our digital assistant. Responses can make mistakes. Chat sessions are recorded. Verify important information before acting. About using Ask Anton
By sending a message, you agree to our Terms of Use, including arbitration and use of your submissions in content, and acknowledge our Privacy Policy.